2026 Bridge rebuild at Nottawasaga Bluffs Lookout Side Trail

  • In the winter of 2025, a small bridge that crossed Leys Burn Creek, located on the Nottawasaga Bluffs Lookout ST, was damaged due to a heavy snow load.
  • By March 2026, the NVCA approved our permit application to build a stronger “truss” style bridge to replace the damaged bridge. 
  • As a first step, wire-mesh gabion baskets were installed on both banks of the creek, approximately 30 metres upstream of the previous bridge location.
  • The cribs were dismantled at the old bridge site, and those rocks were then relocated to fill the gabion baskets.
  • A single ‘test’ truss was constructed using the old lumber salvaged from the former bridge.
  • Work will continue on assembling two additional trusses.
  • Once all the trusses are completed, they will be fastened onto the gabions, and the decking can then be installed.
  • The final step will be the placement of access ramps on either side of the bridge.
  • Stay tuned for further updates.